Heating system:
The central heating plant was installed to cover nursery’s heating loses was 1.200.000Kcal (1,42MW), by using Diesel for fuel. The boiler room is consisted of:
- 1 steel boilers with diesel burner
- 2 water collectors, with 1 water pump.
- steel pipes for the circulation of the water
The heat exchange was done by:
- Onfloor heating steel pipes
- Unit heaters FCH 160, produced by Megatherm
The heating steel pipes along with the unit heaters FCH, make an ideal system for heat transfer in the greenhouse, because both the heating of the plant’s root and the heating of the space are achieved.
Owner:
Farma Plant
Project location:
Νάουσα
Project area:
5.000 sq.m.
Date:
2009 