Selected Works
Heating system:
The central heating plant was installed to cover nursery’s heating loses was 1.200.000Kcal (1,42MW), by using Diesel for fuel. The boiler room is consisted of:
- 1 steel boilers with diesel burner
- 2 water collectors, with 1 water pump.
- steel pipes for the circulation of the water
The heat exchange was done by:
- Onfloor heating steel pipes
- Unit heaters FCH 160, produced by Megatherm
The heating steel pipes along with the unit heaters FCH, make an ideal system for heat transfer in the greenhouse, because both the heating of the plant’s root and the heating...
Heating system:
The central heating plant was installed to cover greenhouse’s heating loses was 1,000,000Kcal (1.16MW), by using LPG for fuel. The boiler room is consisted of:
- 2 steel boilers with LPG burners, 500,000Kcal each.
- 2 water collectors with 2 water pumps.
- steel pipes for the circulation of the water
The heat exchange was done by:
- Onfloor heating plastic pipes (Geotherm)
- Unit heaters FCH 40, produced by Megatherm
The heating plastic pipes (Geotherm) along with the unit heater FCH, make an ideal system for heat transfer in the greenhouse,...
Heating system:
The central heating plant was installed to cover greenhouse’s heating loses was 800.000Kcal (950kW) by using Diesel for fuel. The boiler room is consisted of:
- 1 steel boiler with one burner.
- 2 water collectors, with 2 water pumps.
- steel pipes for the circulation of the water
The heat exchange was done by:
- Onfloor heating plastic pipes (Geotherm)
Spraying system:
The spraying system installed in the greenhouse is consisted of:
- 2 LVM 2001 TR, which are fixed in...
Heating system:
The central heating plant was installed to cover greenhouse’s heating loses was 6,000,000Kcal (7.00MW), by using mazout for fuel. The greenhouses were devides in three blocks, one close to another. So, the heating system is devided in three boiler rooms as well, consisted of:
- 5 steel boilers with mazut burners
- water collectors to distribute the water in the greenhouses.
- steel pipes for the circulation of the water
The heat exchange was done by:
- Onfloor heating steel pipes
- Unit heaters FCH 60, produced by Megatherm
The heating steel...